Replacement of the Heating System - University Centre LRC

February 29th, 2008

 

For those of you who are regular users of the LRC at the University Centre (High Melton), you will be aware that we have experienced problems with the heating system over recent years.

 

You will therefore, be pleased to know that the system is being replaced over the next few weeks. Whist we do not expect the work to impact upon services and/or access to the LRC, the following is a week-by-week summary of what is likely to be happening.

 

Check this space for updates or changes to the heating works. Don’t forget, if you have any questions just ask a member of staff.

 

Week commencing 3rd March 2008

 

CITS will be moving the open access PCs in the main area of the LRC so that the contractors can have a ‘walkway’ around the outside of the main area to enable them to bring in equipment and machine. Other areas of the LRC will be ‘cleared’ to allow the contractors access.

 

Week commencing 10th March 2008

 

Site set up – contractors will prepare the site for the commencement of work. This will mean areas of the LRC will be sectioned-off so that contractors can work without disturbing LRC users. The main area of work is the installation of a staircase to the roof space so that the heating system can be accessed and maintained. It is expected that the staircase will be delivered in sections on Sunday 16th March.

 

Weeks commencing 17th March & 24th March 2008

 

Much of the work around this fortnight will be concerned with the installation of the staircase within the main area of the LRC and also the installation of new condensing units to operate the new system. The area near the journal display units and the reference collection is where the new staircase will be located. The area will be screened-off so noise and dust levels will be kept to a minimum. The remainder of the work will take place in the roof space above ceiling level, so again, disruption should be minimal.

 

Weeks commencing 31st March & 7th April 2008

 

Most of the ‘heavy’ work will have been completed by this stage and the main activity will be removal of hoardings and site clearance, with a view to the works being completed week commencing 14th April 2008.

 

All services are expected to run as normal, but please check the blog for any last minute changes to the schedule.

 


AutoCAD new for use in the LRC

February 7th, 2008

 

AutoCAD (Computer Aided Design) software is now available to book for use on one of HUBs own Learning Resource Centre computers. This is brand new and will be a big asset to all sorts of design based modules and courses, with a special relevance to all our engineering students.

 

Students may book this computer with AutoCAD on through LRC staff at the Level 3 reception.

 

Comments

Investors in People  DisabledGO   The Matrix Standard  European Social Fund

Copyright © Doncaster College 2012

Email - Online Contact form

Telephone - 01302 553 553

Contact us | T&Cs | Privacy | Contact the webmaster | Freedom of Information